The Katabello — construction progress · August 2026
Overall progress
16.1%
Official developer stage breakdown: PILING 100%; STRUCTURE 43.9%; ARCHITECTURE 1.8%; SYSTEM INSTALLATION 2.6%.
PILING100%
STRUCTURE43.9%
ARCHITECTURE1.8%
SYSTEM INSTALLATION2.6%
July 2026
The Katabello — construction progress · July 2026
Overall progress
8%
Official developer stage breakdown: PILING 100%; STRUCTURE 22.2%; ARCHITECTURE 1.02%; SYSTEM INSTALLATION 1%.
PILING100%
STRUCTURE22.2%
ARCHITECTURE1.02%
SYSTEM INSTALLATION1%